Updated Mechanic’s Lien/Stop Notice/Payment Bond Form Effective July 1, 2012

What Every Construction Contractor Needs to Know About Upcoming Changes to Mechanic’s Lien and Stop Notice Laws

The following article was contributed by the law firm of Atkinson, Andelson, Loya, Ruud & Romo.

The California Legislature has enacted Senate Bill 189 which makes extensive changes to the mechanic’s lien and stop notice laws effective July 1, 2012. As participants in the construction industry, it is essential that SCGMA members become familiar with the changes to protect their legal rights and interests. This article is not intended to provide an exhaustive review of all of the changes contained in the legislation, but rather an overview of the noteworthy changes.

Preliminary Notice: On a private works, direct contractors must now serve a preliminary notice on the construction lender only. By way of review, the preliminary notice is a prerequisite to enforce any mechanic’s lien, stop notice or payment bond claim.

Waiver and Release Forms: The conditional and unconditional waivers and releases upon progress and final payments, formerly Civil Code Section 3262, have been “recast for clarity” at Civil Code Sections 8132-8138. The forms are completely reformatted with bold notice language at the top of the forms. All forms have added a line for identification of the waivant’s customer. The Conditional Waiver and Release on Progress Payment adds language relating to progress payments covered by previous releases that have not been paid. It should be noted that waiver and releases are void and unenforceable unless they are substantially in the form prescribed by statute.  To download the updated forms click on the links below –

Mechanic’s Lien Change: SB 189 carries forward another recent statutory change to the mechanic’s lien that became effective on January 1, 2011. A claimant must serve the mechanic’s lien and a new “Notice of Mechanic’s Lien” on the owner by either registered, certified, or first class mail, and show proof of service, before the claimant can record the lien. Also, SB 189 will require the claimant’s address to be included on the lien form as of July 1, 2012.

Notice of Completion and Completion: The time in which an owner can file a Notice of Completion is extended from 10 days to 15 days. If there are multiple direct contractors, the owner may record a separate notice of completion with respect to the scope of work under each direct contract. Additionally, on a private work of improvement, “completion” can no longer be accomplished by the “acceptance of the owner” method previously allowed.

Lien Release Bond: The amount of the bond to be given in order to cause the release of the real property from the effect of the lien is reduced from 150% to 125% of the lien amount.

Construction Loans: Both direct contracts (meaning contracts between an owner and contractor) and subcontracts must provide a space for the identification of any construction lender(s).

Standardized Notices: Various notices are required to be given under the mechanic’s lien statutes. The notice content and procedure requirements are now standardized. For example, all such notices must include information, to the extent known, for the following: (a) name and address of owner or reputed owner; (b) name and address of direct contractor; (c) name and address of construction lender, if any; (d) description of the site sufficient for identification; (e) name and address and relationship to the parties of the person giving the notice; and (f) if the person giving the notice is the claimant, then the notice must also include a general statement of the work provided, the name of person to whom it was provided to and a statement or estimate of the claimant’s demand after deducting any credits or offsets. Notice is not invalid by reason of any variance from these requirements if the notice is sufficient to “substantially inform” the person given the notice of the information required.

In addition, the changes now standardize the means by which a claimant or other interested party may serve notice and provide proof of service. Notices can now be served by express mail or overnight delivery by an express service carrier, as well as by the previously allowed personal delivery and delivery given by registered or certified mail. To prove service, a claimant must provide a “proof of notice declaration,” and if served by mail, evidence of mailing, including but not limited to, documentation provided by the post office showing that payment was made to send the notice. Thus, although still sufficient, the signed “green card” is no longer mandatory if the claimant can provide other forms of proof of service designated by the new notice provisions.

Terminology: The new statutes re-define some terms: “original contractor” is now recast as a “direct contractor”, which means a contractor who holds a contract with a project owner. “Material supplier” has replaced the outdated term “materialman.” The term “stop payment notice” replaces “stop notice.” The “Preliminary 20-Day Notice” is now simply the “Preliminary Notice.

Once again, the changes take effect July 1, 2012. Please contact us if you have any questions regarding the changes in the law.

 


 

 

Atkinson, Andelson, Loya, Ruud & Romo has extensive knowledge of public and private works construction issues and has represented numerous owners, general contractors, and subcontractors in a variety of transactions and disputes.

 


 

 

Thomas W. Kovacich, Esq.
Anthony P. Niccoli, Esq.
Atkinson, Andelson, Loya, Ruud & Romo
Main (562) 653-3200 * Fax (562) 653-3333
www.aalrr.com; tkovacich@aalrr.com; aniccoli@aalrr.com

Recent Posts

SCGMA Technical Bulletin – Low E Glass: A Historical Review

Low E Glass represents one of the greatest advancements in the energy efficiency of modern-day glass products, from common residential uses to iconic commercial projects. Low E glass has transformed the glazing world and promoted the greater use of glass…

December 24, 2025

SCGMA YPG Event Recap – Access Hardware Supply Tour

On Friday, December 19, our Young Professionals gathered at Access Hardware Supply’s new Southern California distribution center in Rancho Cucamonga for an engaging morning focused on door and security hardware solutions for glazing projects. The event kicked off with a…

December 23, 2025

SCGMA YPG Access Hardware Supply Tour

Join us for a tour of Access Hardware Supply’s new Southern California center in Rancho Cucamonga and discover how to optimize hardware selection for glazing projects. Attendees will learn how to choose the right security locks and safety door hardware…

November 19, 2025

SCGMA YPG Event Recap – 2025 Glazing Boot Camp & Water Testing Demo

On October 16th, we hosted another successful Glazing Boot Camp featuring a water testing demo at our Apprenticeship Training Facility in Commerce. The event kicked off with an engaging presentation on what it takes to be a glazier, setting the…

October 21, 2025

SCGMA Event – General Membership Meeting

Join us to learn more about Association happenings – trust fund updates, industry updates, man hour updates, and more. Date: Friday, November 14, 2025 Time: 7:00am – 7:30am Location: via Zoom Meeting Agenda: 1. Call to Order 2. SCGMA Open Session…

October 20, 2025
MORE STORIES